Dave Hand edited this page Oct 22, 2013 · 29 revisions

Project Web Site

TCNJ Senior Project Proposal (.docx)

Design Figure ([.png] (https://github.com/davehand/three_phase_relay/blob/master/Documentation/SMART_Figure.png))

Gantt Chart ([.xls] (https://github.com/davehand/three_phase_relay/blob/master/Documentation/Gantt_Chart.xls))

PDR ([.pdf] (https://github.com/davehand/three_phase_relay/blob/master/Documentation/PDR.pdf))

Business Plan ([.docx] (https://github.com/davehand/three_phase_relay/blob/master/Documentation/Business_Plan.docx))

Marketing Plan ([.docx] (https://github.com/davehand/three_phase_relay/blob/master/Documentation/Marketing%20Plan.docx))

Three-Phase Relay Design ([.pdf] (https://github.com/davehand/three_phase_relay/blob/master/Documentation/Three_Phase_Relay_iPhone.pdf))

Open Source Software utilized:
GPS parsing library - http://arduiniana.org/libraries/tinygps/

###Weekly Progress:

10/17/13 - Eddie and Dave successfully connected the GPS and Wifi shield with the Arduino. Time stamps were successfully taken from the GPS and output to the computer.

10/14/13 - Met with Dr. Deese to discuss progress. He wants to see some output from GPS and Arduino connection as well as some output from circuit and Arduino connection.

10/9/13 - Met as a class for the seventh time this semester. Submitted and discussed business plans. Discussed developing a marketing plan, which is due in two weeks.

10/7/13 - Met with Dr. Deese. Completed overview of mock up, which Deese liked. Will make some adjustments and then begin development.

10/5/13 - Eddie and Dave created Mock up UI for the iPhone and Web Application. Uploaded images to GitHub and Google Drive.

10/3/13 - Dave: Wrote and revised the business plan for our company. Uploaded plan to GitHub and Google Drive.

10/2/13 - Met as a class for the sixth time this semester. Discussed business plan ideology. Business plans are due next week.

9/30/13 - Met with Dr. Deese as a team to discuss the progress on both hardware and software. Dr. Deese told us to order the GPS we found. Steve and Tim need to finish implementing circuits in hardware. Eddie and I need to build a mock up of the application for next week.

9/29/13 - Eddie and Dave: Researched various GPS systems for use with Arduino project. Selected one to present to Dr. Deese. Wrote code for getting time stamp from GPS.

9/25/13 - Presented website design today at fifth senior project class of the semester. Discussed our design ideas for the site and got feedback from others and their designs.

9/24/13 - Eddie: Completed website design. Posted link above for reference. Closed issue.

9/23/13 - Eddie and Dave: researched setting up the wifi network with the shield and decoding and using GPS signals. Found code to set up wifi and a library for parsing the GPS.

9/22/13- Tim and Steve: Initial bread boarding and testing of circuitry was started.

9/18/13 - Presented PDR today at fourth senior project class of the semester. Discussed our design ideas as well as our planned course of action. Question about safety specifications was raised. Something to look into.

9/17/13 - Met as a group to write PDR. Discussed different aspects of design and created slides as a group. Presenting the PDR tomorrow.

9/11/13 - Met for third senior project class of the semester. Discussed specifications and constraints form to be completed. Also discussed PDR (Preliminary Design Review) due next week.

9/4/13 - Presented Gantt chart at second senior project class of the semester. Made minor revisions based on feedback.

9/2/13 - All 4 team members met to discuss and create the Gantt chart for our project. We also procured notebooks.

8/28/13 - First senior project class of the semester. Reviewed course requirements. Presented proposal to rest of senior class.