Implementation Timeline

This document outlines the high level delivery plan for the first six to eight weeks of development. Each task references the corresponding feature IDs from the Product Requirements document and the tracking issues on GitHub.

Week 1-2: Critical MVP Features

Week 3-4: Core Enhancement

  • Implement Overrides Listener (F-2-1) – Issues #102, #106
  • Enhance Metrics (F-1-8) – Issue #103

Week 5-6: Testing & Polish

  • Comprehensive Testing – Issue #111
  • Documentation & Examples – Issue #112
  • Performance Testing – Issue #115
  • Risk Mitigation – Issue #114

Success Criteria

  • MVP Completion (Week 2) – Issue #113
  • Production Ready (Week 6)

This plan is used by the create_issues_from_plan.py script to generate GitHub milestones and issues automatically. Update the check boxes above as tasks are completed to track progress.